        對竣工試驗的干擾

        時間:2023-09-23 百科知識 版權(quán)反饋
        【摘要】:如果由于進(jìn)行竣工試驗的此項拖延,使承包商遭受延誤和(或)招致增加費用,承包商應(yīng)向雇主發(fā)出通知,有權(quán)根據(jù)第20.1款[承包商的索賠]的規(guī)定提出:If the Contractor is prevented, for more than 14 days, from carrying out the Tests on Completion by a cause for which the Employe

        如果由雇主應(yīng)負(fù)責(zé)的原因妨礙承包商進(jìn)行竣工試驗達(dá)14天以上,承包商應(yīng)盡快地進(jìn)行竣工試驗.      

        如果由于進(jìn)行竣工試驗的此項拖延,使承包商遭受延誤和(或)招致增加費用,承包商應(yīng)向雇主發(fā)出通知,有權(quán)根據(jù)第20.1款[承包商的索賠]的規(guī)定提出:

        (a) 根據(jù)第8.4款[竣工時間的延長]的規(guī)定,如果竣工已或?qū)⑹艿窖诱`,對任何此類延誤給予延長期;

        (b)  對任何此類費用,加合理的利潤,應(yīng)加入合同價格,給予支付.

        雇主受到此通知后,應(yīng)按照第3.5款[確定]的規(guī)定,對這些事項進(jìn)行商定或確定.

        If the Contractor is prevented, for more than 14 days, from carrying out the Tests on Completion by a cause for which the Employer is responsible, the Contractor shall carry out the Tests on Completion as soon as practicable.

        If the Contractor suffers delay and/or incurs Cost as a result of this delay in carrying out the Tests on Completion, the Contractor shall give notice to the Employer and shall be entitled subject to Sub-Clause 20.1 [Contractors Claims] to:

        (a) an extension of time for any such delay, if completion is or will be delayed, under Sub-Clause 8.4 [Extension of Time for Completion], and

        (b) payment of any such Cost plus reasonable profit, which shall be added to the Contract Price.

        After receiving this notice, the Employer shall proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or determine these matters.